MILL WORKING PARTIES 2011
Wicken Windmill needs volunteers!

Spring Work-in
May 7th to 15th
Provisional Plan
  • Repaint sail shutters
  • Commission eastern set of stones, including bin to Stone Floor chute
  • Work on combined operation of east stones and jogging screen
  • Continue restoration of centrifugal flour dresser
  • Sack Traps, bin floor
  • Continue repair of 'Coton' hurst frame set, and Coton Shed
  • Limewash bin floor
  • New storage for nuts, bolts etc
Late Summer Work-in
August 27th to September 4th
Provisional Plan
  • Work up replacement sail clamps
  • Continue sail shutter refurbishment
  • Repaint roof and dantail, using cherry picker
  • Continue work on centrifugal flour dresser
  • Continue work on Coton mill shed

Contact: Dave Pearce 01664 822751, davepearce7@gmail.com